Case study at shams Camp: Beam and block floor slab installation

Project Overview

Case Study at Shams Camp

Shams Camp, located in the picturesque Ngong Hills of Kenya, faced an urgent challenge when the client required a 37-square-meter first-floor slab installation. Any delay would have disrupted bookings and affected revenue. To meet the tight deadline, the team selected a beam and block floor slab, known for its quick installation and structural efficiency.

Client Requirements

Client Requirements

The client urgently needed a durable first-floor slab installed within a week to prevent booking disruptions at Shams Camp. Therefore, the project required balancing speed, quality, and stability to meet these critical demands.

Choice of Beam and Block Floor Slab

To ensure rapid construction and structural efficiency, Shams Camp opted for a beam and block floor slab. This method strategically placed precast concrete beams across the span, with concrete blocks filling the gaps. Moreover, its minimal on-site concrete pouring allowed for significantly faster completion.

Key Advantages of Beam and Block for Time-Sensitive Projects

Speed of Installation:

Since precast components were manufactured off-site, they allowed for quick and seamless assembly. Consequently, this speed was essential to meeting the tight deadline.

Minimized On-Site Concrete Work:

Unlike traditional methods, this system significantly reduced on-site concrete pouring, thereby cutting curing time and accelerating overall completion.

Structural Efficiency:

The combination of precast beams and blocks not only created a strong and durable floor but also ensured the client’s expectations were met effectively.

Reduced Disruption to Operations:

Because the installation process was both quick and required minimal on-site work, normal operations continued smoothly, allowing uninterrupted bookings.

Project Execution

To guarantee success, the team meticulously planned the timeline, ensuring the slab was completed within a week. Additionally, precast components were specifically designed to fit the 37-square-meter area, arriving ready for swift assembly and thereby meeting the client’s urgent needs.

Outcome

As a result, the team installed the beam and block slab on time, ensuring uninterrupted bookings. Ultimately, the client highly appreciated the construction’s efficiency and quality.

Conclusion

This case study clearly shows that the beam and block system offers an ideal solution for time-sensitive projects. It provides fast installation, ensures structural strength, and reduces on-site work, making it the preferred choice for urgent timelines. Consequently, Shams Camp met its construction goals on time, demonstrating the system’s exceptional value in fast-paced hospitality projects.

Case study at Shams Camp

Client Requirements

The client urgently requested a durable first-floor slab and set a one-week deadline to prevent booking disruptions at Shams Camp. Therefore, the team balanced speed, quality, and stability to meet these critical demands.

Choice of Beam and Block Floor Slab

To ensure rapid construction and structural efficiency, the team at Shams Camp chose a beam and block floor slab. They strategically placed precast concrete beams across the span and filled the gaps with concrete blocks. Moreover, they minimized on-site concrete pouring, which significantly accelerated completion.

Key Advantages of Beam and Block for Time-Sensitive Projects

Speed of Installation:

Since the team manufactured precast components off-site, they quickly and seamlessly assembled them on-site. Consequently, this speed was essential to meeting the tight deadline.

Minimized On-Site Concrete Work:

Unlike traditional methods, this system significantly reduced on-site concrete pouring, thereby cutting curing time and accelerating overall completion.

Structural Efficiency:

The combination of precast beams and blocks not only created a strong and durable floor but also ensured the client’s expectations were met effectively.

Reduced Disruption to Operations:

Because the installation process was both quick and required minimal on-site work, normal operations continued smoothly, allowing uninterrupted bookings.

Project Execution

To guarantee success, the team meticulously planned the timeline and completed the slab within a week. Additionally, they designed precast components to fit the 37-square-meter area and delivered them ready for swift assembly, meeting the client’s urgent needs.

Case study at Shams Camp
Case study at Shams Camp

Outcome

As a result, the team installed the beam and block slab on time, ensuring uninterrupted bookings. Ultimately, the client highly appreciated the construction’s efficiency and quality.

Conclusion

This case study clearly shows that the beam and block system offers an ideal solution for time-sensitive projects. It provides fast installation, ensures structural strength, and reduces on-site work, making it the preferred choice for urgent timelines. Consequently, Shams Camp met its construction goals on time, demonstrating the system’s exceptional value in fast-paced hospitality projects.